SAMPLE SEGMENT OF THE CHECK OFF LIST
[ RETURN TO HOMEPAGE ]
[ ] DIG COLUMN FOOTERS OR DIG FOOTERS FOR BASEMENT LOAD WALLS
[ ] INSTALL HORIZONTAL REBAR
[ ] INSTALL VERTICAL J BAR
[ ] FOOTER INSPECTION
[ ] POUR CONCRETE FOOTERS
[ ] DECIDE IF USING CEMENT BLOCK UNITS OR POURED WALL SYSTEM
[ ] ORDER MATERIALS FOR BASEMENT OR CRAWL SPACE WALLS;
IF USING BLOCK HAVE DELIVERED AFTER FOOTER PINS HAVE BEEN PLACED
[ ] RE LAY OUT BUILDING CORNERS WITH TRANSIT, INSTALL CORNER PINS